Shield tunnel construction involves numerous risk factors that fluctuate over time, making accurate safety predictions challenging. To solve this, the study's authors established a comprehensive indicator system that evaluates static and dynamic variables separately before integrating them.
Methodology and Validation
The research team utilized 11 static risk factors alongside a particle swarm optimization-support vector machine (PSO-SVM) model to predict baseline static risk levels. For dynamic risks, five factors were monitored using a sliding window combined with a back propagation neural network (BPNN) for data prediction and dynamic weight analysis. Dynamic risk levels were then predicted using a matter-element extension model (MEEM) paired with monitoring data.
Finally, a Bayesian network (BN) synthesized the static and dynamic evaluation results to determine an overall comprehensive risk level. The newly developed model was successfully validated using the tunnel project of the Chushandian Reservoir Irrigation District in China.
Application results across ten cases showed that six instances registered static risk levels ranging from Level 3 to 5. During the specific prediction period (T-5), cases 5, 7, and 9 indicated a dynamic risk level of Level 3, while the comprehensive risk levels for each case settled logically between their individual static and dynamic evaluation scores.